The Annie and Oak Street Issues: Bozeman’s Second High School Faces New Challenges

While the overall design for Bozeman’s 2nd high school has been approved, the actual design drawings will be completed sometime this month, at which time the School Board will take its final vote on the design. Previously, we had learned that the design was modern and sleek, with elements of brickwork, black metal cladding and an all-glass entryway incorporated into the plans. Only small modifications to this design have been made by Building Committee members, which include using traditional red brickwork rather than the originally proposed grey, and using white instead of purple for the triangle outside the main entry.

The Annie Street Issue

City staff members are in favor of the school district building Annie Street east-west, which would cut through the middle of the property where the high school will be constructed. This expense is estimated at $800,000, and would require students to cross a city street in order to reach the playing fields. While the school conducted a traffic study and found that Annie isn’t a heavily used street, the city feels as though building this street is needed for the transportation system.

The Oak Street Issue

While the school had discussed using a portion of the budget to build a soccer field and parking lot on the north side of Oak (across the street from the new school), designers have other plans— building a pedestrian tunnel under Oak Street AND constructing an overpass over the tunnel.

The land north of Oak is city-owned, which means that the plans for a field and parking lot would be a collaborative project with the city’s plans to develop a sports complex. Creating both a tunnel and overpass, while great for ensuring pedestrian safety, present the challenge of meeting the budget.

The goal budget is between $76 million and $78 million, the current design is around $87 million, and once site work, streets and the possible tunnel are factored in, the entire project will cost $93 million.

Future Location of Second High School/Sports Complex

Only Time Will Tell

The Annie Street issue will be discussed as soon as next week, although we aren’t sure when we’ll find out whether the tunnel and overpass project will move forward. Revisiting the budget and cutting costs will likely need to happen before any major decisions are made. Sometime after the new year, however, we can expect to find out more about the new school’s colors, logo and mascot.